Sealcoating Deer Run Schedule & phasing map

We will be sealing the roads maintained by the HOA this year.
This is a little tricky to split up, our contractor has decided the best way to keep traffic flowing is to seal in 4 phases.
The schedule is as followed:
Monday Sept 22nd Green (delayed due to weather)
Wednesday Sept 24th Blue
Friday Sept 26th Red
Monday 29th Yellow
A few things to keep in mind:
All work is weather-permitting, so there could be additional delays.
Thank you for your patience as we maintain our beautiful community.
There is a day left between each phase, in order to allow everyone time to move their cars back to the section that was just sealed, once it is safe to do so.
Typically 24 hours are needed for everything to cure properly.
Please do not move any of the cones set in place by the vendor; the vendor will come around and remove the cones once it is safe to drive on the surface.
Any resident found moving cones will be held liable for any damages done to the project.
Also, any resident who has their vehicle parked in such a way that impacts the scheduled work, is subject to be towed at owner’s expense.